ZORLU ENERJI: ALASEHIR I JEOTERMAL SANTRALI KISMEN FAALIYETE GECTI

14.09.2015 09:02

ZORLU ENERJI ELEKTRIK URETIM A.S. `NIN KAMUOYU AYDINLATMA PLATFORMU`NDA (KAP) YAYINLANAN ACIKLAMASI ASAGIDA BULUNUYOR:

SIRKETIMIZIN % 100 ORANINDA HISSEDARI OLDUGU ZORLU JEOTERMAL ENERJI ELEKTRIK URETIMI AS TARAFINDAN MANISA`NIN ALASEHIR ILCESINDE YAPIMI DEVAM EDEN 45 MW KURULU GUCE SAHIP ALASEHIR I PROJESI KAPSAMINDAKI JEOTERMAL SANTRALININ 33,73 MW`LIK ILK FAZININ PERFORMANS VE GUVENILIRLIK TESTLERI BASARIYLA TAMAMLANMIS OLUP, BAKANLIK RESMI KABULUNUN YAPILMASININ ARDINDAN, SANTRAL 12.09.2015 TARIHI ITIBARIYLA TICARI ELEKTRIK SATISINA BASLAMISTIR. GERI KALAN 11,27 MW`LIK KAPASITENIN EKIM AYI ICINDE ISLETMEYE ALINMASI HEDEFLENMEKTEDIR.